Road Maintenance Update

Road Report for the week of July 28th to August 1st, 2025:

 

Graders:

  • Division 1 - 1 grader working North of Highway 302, from Church Road going West
  • Division 2 - 1 grader working on Miller Drive construction
  • Division's 3 & 5 - 2 graders working from Davis Road, moving South
  • Division's 4 & 6 - 2 graders working on Lincoln Park Road and Deer Park Road

 

Gravel:

  • Division 1 - Construction spots as needed on River Road
  • Division 2 - Swaby Road receiving 1 mile of gravel, from Hazelwood Road to Colleston Road
  • Division 2 - Soft spots on River Road
  • Division 3 - Davis Road receiving 1 mile of gravel

 

Shop:

  • Repairing 5th wheel plate on gravel trailer
  • Replacing oil indication wiring on grader

 

For areas of concern, please contact the RM office at (306) 763-2469 to place a work order.