Road Maintenance Update

Road Report for the week of September 29th to October 3rd, 2025:

 

Graders:

  • Division 1 - 1 grader working on River Road, moving South
  • Division 2 - 1 grader working on River Road, moving South
  • Division 3 - 1 grader working on Osborne Road, moving North
  • Division 4 - 2 graders working Deer Park Road, moving North
  • Division 5 - 1 grader working on 48 Street East construction

 

Gravel:

  • Stockpiling gravel in shop yard

 

Construction:

  • Division 3 - culvert installation on approach near Fenton Ferry Road
  • Division 6 - preparing for clay clapping to take place on Hrynuik Road

 

Shop:

  • Safety inspections on trucks, along with the repairs required

 

For areas of concern, please contact the RM office at (306) 763-2469 to place a work order.