Road Maintenance Update
Road Report for the week of October 20th to October 24th, 2025:
Graders:
- Graders will be in all Division's removing washboards in preparation of winter
Gravel:
- Division 2 - Russ-Stan Road receiving gravel from Spencer Grid to Siwak Road
- Division 4 - Gerrond Road receiving 3 loads of gravel, west of the 4-way stop signs
- Division's 3/5 - Halcro Road receiving gravel from Substation Road going East for 2 miles
Construction:
- Culvert installation along Red Deer Hill Road
- Completion of clay clapping on Hrynuik Road, road will receive gravel by Thursday
Signage:
- Division 3 - Civic Address sign post installation
Shop:
- Safety inspection on Unit #32
- Oil service on Unit #76
- Rear seal replacement on gravel trailer
For areas of concern, please contact the RM office at (306) 763-2469 to place a work order.