Road Maintenance Update

Road Report for the week of August 25th to August 29th, 2025:

 

Graders:

  • Division 1 - 1 grader working from Tower, headed West. 1 grader working on River Road construction site
  • Division's 2 & 3 - 2 graders working from Highway 3, moving East onto Russ-Stan Road
  • Division 6 - 2 graders working North of Tower Road

 

Gravel:

  • Division 1 - road South of church and Lacolle Falls will receive gravel
  • Hauling reject gravel back to shop yard

 

Construction:

  • Division 1 - completion of clay clapping on River Road by mid-week
  • Division 2 - Miller Road reconstruction - weather pending

 

Signage:

  • Civic Address sign installation on Highway 302 East

 

Shop:

  • Oil change on pick up trucks
  • Brakes to be done on trailer tri-axle
  • Organizing road signs 

 

For areas of concern, please contact the RM office at (306) 763-2469 to place a work order.