A A A

Road Maintenance Update

Road Report for the week of July 21st to July 25th, 2025:

 

Graders:

  • Division 2 - 1 grader working on River Road, heading East into Division 1 mid week
  • Division 2 - 1 grader working construction on Aspen Estates Road, headed West to Division's 3 & 5 mid week near Davis Road
  • Division's 2 & 3 - 1 grader working on and around Russ-Stan Road, heading East
  • Division 5 - 1 grader working on Elevator Road, heading South, working in Divisions 3 & 5 near Davis Road

 

Construction:

  • Division 1 - Clay clapping River Road, starting Wednesday
  • Division 2 - Completing Aspen Estates Road levelling
  • Division 2 - Miller Road clay capping, mid week

 

Signage:

  • Division 2 - Civic Address signs to be installed. Completing Aspen Estates and moving to Reid Road and River Road next.

 

Shop:

  • Services on trucks and 2 graders
  • Fifth wheel plate replacement on gravel trailer

 

For areas of concern, please contact the RM office at (306) 763-2469 to place a work order.