Road Maintenance Update

Road Report for the week of September 2nd to September 5th, 2025:

 

Graders:

  • Division 1 - 1 grader working on River Road, moving West into Division 2 
  • Division 2 - 1 grader working on Miller hill construction
  • Division 5 - 2 graders working on Osborne Road, moving East onto Fenton Ferry Road
  • Division 6 - 2 graders working on Lincoln Park Road, moving East to Division 5 Subdivisions

 

Gravel:

  • Division 2 - construction sites on River Road and Miller Hill receiving gravel
  • Stockpiling gravel at Municipal Shop

 

Construction:

  • Miller hill clay clapping to be completed this week

 

Signage:

  • Division 1 - Civic Address sign installation North of River Road
  • Division 2 - Civic Address sign installation to be completed this week

 

Shop:

  • Repair to hydraulic pump on JD 4440
  • Thermostat repair on JD 4455
  • Hydraulic repair on Unit 52 Grader

 

For areas of concern, please contact the RM office at (306) 763-2469 to place a work order.