Road Maintenance Update

Road Report for the week of May 19th to May 23rd, 2025:

 

Grading:

  • Division 1 - 1 grader working in Division 1, starting on Wednesday
  • Division 3 - 2 graders starting on Fenton Ferry Road, 1 grader moving south and 1 grader moving west
  • Division's 4,5,6 - 1 grader working around Tower Hill, moving south
  • Division 5 - 1 grader working on 48th Street East, Elevator Road and Subdivisions around the city
  • Division 6 - 1 grader on Lincoln Park Road and Southview Acres, heading west

 

Gravel:

  • Division 4 - 2 areas receiving gravel on Deer Park Road - area along the South Saskatchewan River, and 2 miles in between Red Deer Hill Road and Donny Brook Road
  • Division 5 - Silver Willows gravel to be completed on Tuesday

 

Construction:

  • Silver Willows ditch sloping and clean up debris to be completed by Friday
  • Civic Address sign installation will continue in Division 1

 

Shop

  • Semi crossmember being repaired Tuesday and Wednesday
  • Safety on Tandem truck being worked on
  • Rock truck shock maintenance

 

For areas of concern, please contact the RM office at (306) 763-2469 to place a work order.