A A A

Road Maintenance Update

Road Report for the week of July 14th to July 18th, 2025:

 

Graders:

  • Division 1 - 1 grader working from East to West
  • Division 2 - 1 grader working from East side of Russ-Stan Road. moving West
  • Division's 3 & 5 - 2 graders working from Davis Road, moving South
  • Division 4 - 2 graders working on Deer Park Road, moving North into Division's 5 & 6

 

Construction:

  • Division 1 - River Road visibility being improved by lowering 1 hill
  • Division 2 - Miller Road visibility improvement by levelling road
  • Division 2 - MG 30 application starting Wednesday on Aspen Estates Road

 

Mowing:

  • Division 3 - along Fenton Ferry Road

 

Signage:

  • locates and sign locations being flagged all week

 

Shop:

  • Gravel trailers safety inspections to be completed early this week

 

For areas of concern, please contact the RM office at (306) 763-2469 to place a work order.