Road Maintenance Update
Road Report for the week of July 14th to July 18th, 2025:
Graders:
- Division 1 - 1 grader working from East to West
- Division 2 - 1 grader working from East side of Russ-Stan Road. moving West
- Division's 3 & 5 - 2 graders working from Davis Road, moving South
- Division 4 - 2 graders working on Deer Park Road, moving North into Division's 5 & 6
Construction:
- Division 1 - River Road visibility being improved by lowering 1 hill
- Division 2 - Miller Road visibility improvement by levelling road
- Division 2 - MG 30 application starting Wednesday on Aspen Estates Road
Mowing:
- Division 3 - along Fenton Ferry Road
Signage:
- locates and sign locations being flagged all week
Shop:
- Gravel trailers safety inspections to be completed early this week
For areas of concern, please contact the RM office at (306) 763-2469 to place a work order.