Road Maintenance Update
Road Report for the week of May 5th to 9th, 2025:
Grading:
- Division 1 - 2 graders finishing up around the Birson area and will be moving into south of Division 2
- Division's 3 & 5 - 2 graders working in between Highway 3 and Highway 2
- Division 4 - 2 graders working on Red Deer Hill Road and moving south into Division 4
- Division 5 - Grading around the city will take place in the later part of the week
Gravel:
- Division 1 - River Road soft spots
- Division 2 - needed areas on Russ-Stan Road
- Division 6 - Hrynuik Road soft spots
- Stock piling gravel Thursday and Friday
Construction:
- Culvert repair on Hrynuik Road
- Washout repair on Lindsay Road
- Sign installation for Civic Addressing
- Gravel reclamation along Meridian Road
Shop:
- Installation of sprayer for weed control
- Repairs to tractor steering
- Repairs to gravel trailers
- Maintenance to mowers
For areas of concern, please contact the RM office at (306) 763-2469 to place a work order.