Road Maintenance Update

Road Report for the week of June 9th to June 13th, 2025:

 

Grading:

  • Division 1 - 1 grader working south of Highway 302 East, moving North across Highway 302 - mid week
  • Division 2 - 1 grading and 3 blading on Fenton Ferry Road, Davis Road, and off of Russ Stan Road 
  • Division 4 - 2 graders heading North on Red Deer Hill Road for Monday, moving into Division 6
  • Division 5 - 1 grader heading around the city, including subdivisions
  • Division 6 - 1 grader working on Dairy Road

 

Gravel:

  • Division 2 - Finish off Russ Stan Road
  • Division 4 - Completing gravel on Red Deer Hill Road construction
  • Division 5 - Construction area on Meridian Road - end of the week

 

Construction:

  • Division 1 - Cutting in ditches and filling in low spots on Twp 490
  • Division 1 - Culvert installation along River road - mid week
  • Division 4 - Repairing a soft spot along Deer Park Road
  • Division 6 - Pulling shoulders and reshaping the North end of Meridian Road, from West Central School to Highway 302 West.

 

Shop:

  • Fixing air leaks on unit 52, on Monday
  • Replacing hydraulic hose on mulcher
  • Services on 2 graders - mid week