Road Maintenance Update
Road Report for the week of October 28th to November 1st, 2024:
Grading:
- Cutting out washboards throughout the RM. Graders are starting in Divisions 1, 4 & 6. Graders will make their way into Divisions 2, 3 & 5 on Tuesday afternoon/Wednesday morning.
Construction:
- Division 1 - Culverts are being installed on RGE RD 2225. Road is closed until further notice.
- Division 1 - building a field access approach on RGE RD 2233.
- Division 1, 2 & 5 - Culvert clearing and maintenance
Signage:
- Divisions 5 & 6 - Replacement signs are being installed beginning of week.
- Divisions 2 & 3 - Replacement signs are being installed mid to end of the week.
Mowers are in Division 6 working to the East.