Road Maintenance Update
Road Report for the week of October 7th to October 11th, 2024.
Grading:
- 2 Graders finishing up in Division 1 on Monday and Tuesday and moving onto Division 2
- 1 Grader in Division 3
- 1 Grader in Division 4
- 1 Grader in Divisions 5 & 6
Gravelling:
- Gravel Stock pile to the yard for the week
Construction:
- Division 6 - Removing excess debris and earth off of shoulder and ditch on Hrynuik Road
Division 5 - Signs to be fixed, including School Speed Sign at Osborne School.
Culvert on McKeen Drive is to be cleaned out.
Mowing to finish off in Division 4 by the end of the week.