Road Maintenance Update

Road Report for the week of October 6th to October 10th, 2025:

 

Graders:

  • Division 1 - 1 grader working on Soloducha Road, moving West
  • Division 2 - 1 grader working on Spencer Grid, moving West
  • Division 3 - 2 graders working on Fenton Ferry Road, moving South
  • Division's 5/6 - 1 grader working on construction near Hrynuik Road and Tower Road
  • Division 6 - 1 grader working on Meridian Road, moving South East

 

Gravel:

  • Stockpiling gravel to the shop yard

 

Construction:

  • Division 6 - clay clapping on Hrynuik Road to start Tuesday. Construction to be completed by end of week

 

Signage:

  • Division 3 - marking locates for Civic Address signage

 

Shop:

  • Repairs on unit #32 Truck
  • Cleaning of grader for sale
  • Trailer seal on unit #29

 

For areas of concern, please contact the RM office at (306) 763-2469 to place a work order.