Road Maintenance Update
Road Report for the week of October 14th to October 17th, 2025:
Graders:
- Division 1 - 1 grader working on River Road
- Division 2 - 1 grader working on Cecil Ferry Road
- Division 4 - 2 graders working on Donny Brook Road
- Division 5 - 1 grader working on Elevator Road and 1 grader working on Lincoln Park Road, moving into Division 6 onto West Central Road
Gravel:
- Division 5 - 48th street receiving gravel
- Stockpiling to shop yard
Mowers:
- Division 3 - Hazelwood Road
Signage:
- Division 3 - Installation of Civic Address sign posts. Starting North of Highway 3 and moving onto Fenton Ferry Road
Shop:
-
Kenworth unit #32 safety maintenance
-
Gravel trailer breaks and seal maintenance
-
Service to JD tractor #4455
For areas of concern, please contact the RM office at (306) 763-2469 to place a work order.