Road Maintenance Update

Road Report for the week of September 15th to September 19th, 2025:

 

Graders:

  • Division 1 - 1 grader working from Sask Forks area, moving West
  • Division's 2&3 - 1 grader working North and South bound of Russ-Stan Road - starting at Highway 3, moving East
  • Division 3 - 1 grader working around Davis area
  • Division 4 - 1 grader working on construction on Paul Road
  • Division 6 - 2 graders on Meridian Road

 

Gravel:

  • Division 1 - River Road
  • Division 2 - Miller Hill
  • Division 5 - Intersection on Samson Road and Lincoln Park Road

 

Construction:

  • Division 6 - Culvert installation on 6 Mile West Road
  • Division 3 - Culvert installation on Fenton Ferry Road

 

Signage:

  • Division's 2&3 - Civic Address Sign Installation North of Highway 3

 

For areas of concern, please contact the RM office at (306) 763-2469 to place a work order.