Road Maintenance Update June 3rd to June 10th, 2024

the following work is to be completed this week,

Grading this week:

  • Division 2 – Starting on Russtan Road working East
  • Division 3 – Fenton Ferry Road to Halcro Road, moving north
  • Divisions 5 & 6 Lincoln Park Road, starting on the correction line moving East

Graveling this week:

  • Division 2 – Jenik Road, Byrne Road
  • Division 5 – South View Acres entrance
  • Division 3 – John Prince Road and area near Fenton Ferry Road along Highway 3

Construction this week:

  • Culvert replacement on Hazelwood Road
  • Clearing out culvert on Bibby Road

Reclaiming Halcro Road mid week.

Flamans Road finishing off road ditch and surface preparing for gravel.