**Please be advised that this report is subject to change, without notice**
Subdivisions are to be graded every Friday
Graders will be in Divisions One, Two, Three, Five and Six. Graders are set to be in Division Four near the end of this week.
Division One – Mowing to commence Tuesday
Division Two – Ongoing construction on Reid Road (clay capping)
– Detour for HWY 3 on Hazelwood and Russtan Road up until Wednesday
– Repair to Aspen Bay Cul-de-sac
– Gravel placement on Reid Road
Division Three – Gravel placement on Fenton Ferry Road/Fenton Ferry is still closed
Division Six – Beaver Control
The Public Works Department is undergoing training.
We kindly ask that vehicles proceed with caution, for the safety of the RM and our Public Works Department working and training on the roads, please respect speed postings – thank you.